Create a precedence activity network using the following details. You can draw this on paper or use a tool of your choice.
| Activity | Depends on | Duration
(days) |
| A | 5 | |
| B | A | 7 |
| C | B | 6 |
| D | A | 5 |
| E | D | 10 |
| F | B | 15 |
| G | B | 8 |
| H | G | 8 |
| I | C | 4 |
| J | G | 4 |
| K | E,F | 5 |
| L | I,H | 3 |
Calculate the earliest and latest start and end dates and the float associated with each activity. From this identify the critical path.